Freight costs and transit times are rarely a single number. A sea freight quote is a base rate plus a stack of surcharges. An air freight price depends on how much space your cargo takes as much as on its weight. Road freight is often charged by the metre of trailer floor you use. Transit time is the sum of several steps. Only one of them is the actual sailing or flight.
This guide explains how freight prices are built for sea, air and road, how to calculate CBM, chargeable weight and loading metres, what demurrage and detention are and how to avoid them. It also shows what really determines door-to-door transit times between Asia, Europe and the Benelux. All figures are dated and sourced. Where a number depends on your carrier or contract, we say so.
Key takeaways
- The base ocean rate is only part of the price. Fuel, emission, terminal, security and documentation charges are added on top and many of them change every month or quarter.
- Since 2024 carriers pass on the cost of the EU Emissions Trading System (EU ETS) and since 2025 the cost of FuelEU Maritime. Both are rising.
- LCL is priced per W/M (1 CBM or 1,000 kg, whichever is greater). Air cargo uses 1 m³ = 166.67 kg (divisor 6,000), express services 1 m³ = 200 kg (divisor 5,000). Road groupage is often priced per loading metre.
- Demurrage is charged while a carrier’s container stays in the terminal, detention while it is outside. In Belgium, Maersk and Hapag-Lloyd include terminal storage in demurrage.
- Port-to-port sailing time is only one part of door-to-door transit. In August 2026 only 49.9% of vessels worldwide arrived on schedule.
How a sea freight price is built
A container or LCL quote is made up of charges from different parties: the shipping line, the terminals at both ends, the port and security authorities and your forwarder. Knowing which line belongs to whom makes quotes comparable.
Base ocean freight
The base rate covers the sea transport from the port of loading to the port of discharge. For FCL it is quoted per container (for example per 20’ or 40’), for LCL per W/M (see below). Base rates move with supply and demand. Spot rates are valid for a short period, contract rates for a longer agreed period. Always check the validity date: carriers apply the rate and surcharges that are valid on a defined reference date, such as the departure date of the first vessel at the time of booking.
Fuel surcharges (BAF)
The bunker adjustment factor (BAF) passes changes in fuel prices on to the shipper. Carriers use their own names. Maersk calls it the Fossil Fuel Fee and Hapag-Lloyd calls it Marine Fuel Recovery (MFR). Hapag-Lloyd reviews MFR quarterly.
Fuel surcharges can change quickly. After the disruption around the Strait of Hormuz in early 2026, Maersk, CMA CGM, MSC and Hapag-Lloyd added temporary emergency fuel or bunker surcharges from March 2026. Hapag-Lloyd ended its emergency charge on 1 July 2026 when it reset its MFR for the third quarter. When you compare quotes, check whether any temporary surcharge is still included and until when.
Emission surcharges: EU ETS and FuelEU Maritime
Two EU rules now add a cost line to almost every container to or from Europe.
EU ETS. Since January 2024 the EU Emissions Trading System covers CO2 emissions from ships of 5,000 gross tonnage and above. It covers 100% of emissions on voyages between two EU ports and while ships are in EU ports. It covers 50% of emissions on voyages that start or end outside the EU. Shipping companies surrender allowances for a growing share of their emissions: 40% of the emissions reported for 2024, 70% for 2025 and 100% from 2026 emissions onwards. Methane and nitrous oxide are included from 2026.
FuelEU Maritime. Regulation (EU) 2023/1805 has applied in full since 1 January 2025 to ships above 5,000 gross tonnage calling at EU ports, whatever their flag. It requires the greenhouse gas intensity of the energy used on board to fall compared with 2020: by 2% from 2025, 6% from 2030, 14.5% from 2035, 31% from 2040, 62% from 2045 and 80% from 2050.
Carriers pass these costs on under different names. Maersk charges an Emissions Surcharge (EMS for contracts longer than 31 days, ESS for spot bookings and shorter contracts) that covers both EU ETS and FuelEU Maritime. It is recalculated every quarter from the average price of EU allowances and applies when the port of loading or discharge is in the EU or EEA. For the fourth quarter of 2026 Maersk’s Emissions Surcharge from the Far East to North Europe is USD 85 per 20’ dry container and USD 170 per 40’ dry container. Hapag-Lloyd shows its EU ETS surcharge separately and also recalculates it quarterly. Other carriers use other names, so look for any line with “ETS”, “emission” or “energy transition” in it.
Terminal handling charges at origin and destination
Terminal handling charges (THC) pay for moving the container between ship and terminal. There is an origin charge (OTHC or OHC) at the port of loading and a destination charge (DTHC or DHC) at the port of discharge. As an example of the level, Maersk’s destination and origin terminal handling charge for Belgium has been EUR 275 per dry container and EUR 395 per reefer container since 1 October 2026. Other carriers and terminals publish their own amounts.
For LCL there are additional warehouse charges at both ends, because the cargo is received, consolidated, unpacked and handed over at a container freight station (CFS).
Security, documentation and other fixed charges
- ISPS or security surcharge. Covers port and ship security costs under the International Ship and Port Facility Security (ISPS) Code, which entered into force on 1 July 2004 under SOLAS chapter XI-2.
- Documentation fees. For issuing the bill of lading or sea waybill and for other paperwork. More on documents in our guide to shipping documents.
- Currency adjustment factor (CAF). Some carriers and trades add a surcharge to cover exchange rate movements between the currency of the rate and the currency of their costs.
- Customs and inland charges. Customs clearance, inspections and trucking or barge transport to and from the port are separate items. See customs clearance.
Peak season, GRI and temporary surcharges
Carriers announce peak season surcharges (PSS) per trade when demand is high and general rate increases (GRI) when they raise base rates. Contingency surcharges, such as the emergency fuel surcharges of 2026, can be introduced at short notice. Carrier tariffs state explicitly that rates are subject to other applicable surcharges, including local charges and contingency charges.
Table: anatomy of a sea freight quote
| Cost item | Who charges it | Usual basis | How often it changes |
|---|---|---|---|
| Base ocean freight | Shipping line (via forwarder) | Per container (FCL) or per W/M (LCL) | Spot: weekly or per booking; contract: per agreement |
| Fuel surcharge (BAF, Fossil Fuel Fee, MFR) | Shipping line | Per container or per W/M | Monthly or quarterly, plus emergency changes |
| Emission surcharge (EU ETS, FuelEU) | Shipping line | Per container | Quarterly at most large carriers |
| Origin THC | Shipping line or terminal | Per container | Usually yearly |
| Destination THC | Shipping line or terminal | Per container | Usually yearly |
| CFS charges (LCL) | Consolidator or warehouse | Per W/M, often with a minimum | Per tariff |
| ISPS or security surcharge | Shipping line or terminal | Per container | Per tariff |
| Documentation fee | Shipping line or forwarder | Per bill of lading or shipment | Per tariff |
| PSS, GRI, contingency surcharges | Shipping line | Per container | Announced per trade |
| Demurrage, detention, storage | Shipping line or terminal | Per container per day after free time | Per tariff, see below |
| Customs, inspections, inland haulage | Customs broker, authorities, haulier | Per declaration, per inspection, per trip | Per quote |
Units: CBM, W/M, chargeable weight and loading metres
Every transport mode compares weight with space, because a vessel, aircraft or trailer can be full by volume long before it is full by weight. The trick is knowing which conversion each mode uses.
How to calculate CBM
CBM means cubic metre. Multiply length by width by height in metres, using the packed dimensions including the pallet.
CBM = length (m) × width (m) × height (m)
A carton of 60 × 40 × 50 cm is 0.60 × 0.40 × 0.50 = 0.12 CBM. If dimensions are in centimetres, multiply them and divide by 1,000,000.
LCL pricing: W/M and the revenue ton
LCL (less than container load) is charged per W/M, short for weight or measurement. One W/M, also called a revenue ton, is 1 CBM or 1,000 kg, whichever gives the higher number. In practice you compare the volume in CBM with the weight in tonnes and pay on the larger figure. Most tariffs also have a minimum charge and their own rounding rules.
Worked example A (volume decides). For example, a shipment of 25 cartons of 60 × 40 × 50 cm at 18 kg each:
- Volume: 25 × 0.12 CBM = 3.00 CBM
- Weight: 25 × 18 kg = 450 kg = 0.45 tonnes
- Chargeable: 3.00 W/M, because 3.00 is greater than 0.45
Worked example B (weight decides). For example, two pallets of 120 × 80 × 100 cm at 1,200 kg each:
- Volume: 2 × (1.20 × 0.80 × 1.00) = 1.92 CBM
- Weight: 2,400 kg = 2.40 tonnes
- Chargeable: 2.40 W/M, because 2.40 is greater than 1.92
Whether LCL or a full container is cheaper depends on the rates on your lane, the LCL charges at both ends and how fast you need the goods. Our container guide explains container sizes and capacities.
Air freight: volumetric and chargeable weight
Airlines charge on the chargeable weight, which is the higher of the actual gross weight and the volumetric weight. The industry standard set by IATA uses a divisor of 6,000:
Volumetric weight (kg) = length × width × height (cm) ÷ 6,000
Put differently, 1 m³ counts as 166.67 kg (1,000,000 ÷ 6,000). Cargo that is lighter than that per cubic metre is charged on volume.
Worked example C. For example, four cartons of 80 × 60 × 50 cm at 30 kg each:
- Volume per carton: 80 × 60 × 50 = 240,000 cm³; total 960,000 cm³ (0.96 m³)
- Volumetric weight: 960,000 ÷ 6,000 = 160 kg
- Actual weight: 4 × 30 kg = 120 kg
- Chargeable weight: 160 kg
Some airlines use a different divisor and rounding rules differ, so check both on the quote.
Express and courier: divisor 5,000
Express and courier services usually use a divisor of 5,000. DHL Express, for example, calculates length × width × height ÷ 5,000, which means 1 m³ counts as 200 kg. The same four cartons from example C would be charged at 960,000 ÷ 5,000 = 192 kg instead of 160 kg. For light, bulky goods this 20% difference matters when you compare express with air cargo.
Road freight: pallets and loading metres
Full truckloads are priced per trip. Part loads and groupage are priced on the higher of actual weight, volume weight and floor space. Floor space is measured in loading metres (LDM).
One loading metre is one metre of trailer length across the full trailer width of 2.40 m.
LDM = length (m) × width (m) ÷ 2.4
A euro pallet (1.20 × 0.80 m) takes 0.96 ÷ 2.4 = 0.4 LDM and a block pallet (1.20 × 1.00 m) takes 0.5 LDM. A standard trailer has a loading length of about 13.6 m, which is about 33 to 34 euro pallets.
Carriers convert loading metres into a chargeable weight. The factor is not fixed. In Belgium and the Netherlands 1 LDM usually counts as about 1,750 to 1,850 kg and sometimes 1,650 kg. The higher the factor, the more you pay, so always ask which factor your quote uses. For the volume rule many road carriers use 1 m³ = 333 kg.
Worked example D. For example, six euro pallets of 120 × 80 × 120 cm at 450 kg each:
- Actual weight: 6 × 450 kg = 2,700 kg
- Volume weight: 6 × (1.20 × 0.80 × 1.20) = 6.912 m³ × 333 kg = 2,302 kg (rounded)
- Not stackable: 6 × 0.4 = 2.4 LDM. At 1,750 kg per LDM that is 4,200 kg; at 1,850 kg per LDM it is 4,440 kg. Chargeable weight: 4,200 or 4,440 kg, depending on the carrier’s factor.
- Stackable two high: the pallets use three floor positions, so 1.2 LDM. At 1,750 kg per LDM that is 2,100 kg; at 1,850 kg per LDM it is 2,220 kg. Now the actual weight of 2,700 kg is the highest figure and becomes the chargeable weight.
Telling your forwarder whether goods are stackable can therefore change the price considerably. Our guide to pallets and cargo securing covers pallet types and stacking.
Table: what one cubic metre counts for in each mode
| Mode | Conversion | 1 m³ counts as | Note |
|---|---|---|---|
| Sea freight LCL | W/M: 1 CBM = 1,000 kg | 1,000 kg | Higher of CBM and tonnes |
| Road freight (volume rule) | 1 m³ = 333 kg | 333 kg | Commonly used, check your carrier |
| Road freight (floor space) | 1 LDM = about 1,650 to 1,850 kg | depends on height and stacking | Factor differs per carrier |
| Air cargo | divisor 6,000 | 166.67 kg | IATA standard |
| Express and courier | divisor 5,000 | 200 kg | Example: DHL Express |
Air freight costs: what is on the invoice
An air freight invoice typically shows:
- Air freight rate per kilogram of chargeable weight.
- Fuel surcharge per kilogram. Ask whether it is applied to chargeable or actual weight, because airlines handle this differently.
- Security surcharge per kilogram, set by the airline.
- Terminal handling at the departure and arrival airport.
- Documentation, such as the air waybill fee.
- Customs clearance and delivery at both ends.
Because rate, fuel and security charges are all multiplied by the weight, the difference between actual and chargeable weight runs through almost every line. More on our air freight service.
Road freight costs and tolls in Belgium and the Netherlands
Road freight prices reflect distance, the chargeable weight or floor space, waiting and loading times and road tolls. In the Benelux both countries now charge trucks per kilometre. More on our road freight service.
Belgian kilometre charge
Since 1 April 2016 Belgium has charged goods vehicles with a maximum authorised mass above 3.5 tonnes per kilometre. It replaced the Eurovignet in Belgium. Viapass coordinates the system for the three regions. The rate depends on the maximum authorised mass including the trailer, the Euro emission class, the region and the type of road. Since 1 July 2026 Flanders also adds a surcharge based on the vehicle’s CO2 emission class.
At the time of writing (October 2026), a Euro 6 truck above 32 tonnes in CO2 emission class 1 pays EUR 0.285 per km in Flanders, EUR 0.205 per km in Wallonia (excluding VAT) and EUR 0.171 per km on Brussels motorways. In Flanders and Brussels the charge is a tax without VAT. In Wallonia it is a fee subject to VAT.
Worked example E. For example, 120 km on charged roads in Flanders with that truck: 120 × EUR 0.285 = EUR 34.20.
Dutch truck toll (vrachtwagenheffing)
Since 1 July 2026 the Netherlands has charged Dutch and foreign trucks in vehicle categories N2 and N3, with a technical maximum mass above 3,500 kg, per kilometre driven. The charge applies on almost all motorways and on some provincial and municipal roads. Cleaner and lighter vehicles pay less per kilometre. The Eurovignet for the Netherlands ended on the same date. From 1 September to 31 December 2026 the government applies a temporary 22.3% reduction, which it links to sharply higher fuel costs caused by the conflict in the Middle East. Current rates per vehicle are published on vrachtwagenheffing.nl.
Table: truck tolls in Belgium and the Netherlands
| Belgium | Netherlands | |
|---|---|---|
| Name | Kilometre charge (kilometerheffing) | Vrachtwagenheffing |
| In force since | 1 April 2016 | 1 July 2026 |
| Vehicles | Goods vehicles above 3.5 t | N2 and N3 vehicles above 3,500 kg |
| Rate depends on | Mass, Euro class, region, road type, CO2 class (Flanders since 1 July 2026) | Mass and emissions: cleaner and lighter vehicles pay less |
| Roads | Toll road network defined per region (Viapass maps) | Almost all motorways plus some provincial and municipal roads |
| Special point | Three regional rate grids; VAT only in Wallonia | Temporary 22.3% reduction until 31 December 2026 |
Tolls in transit countries are charged on top, so a quote for a long road journey through several countries should state whether all tolls are included.
Demurrage, detention, storage and free time
Demurrage and detention are the charges importers most often do not see coming. They are not part of the freight rate. They start when the free time ends, they are charged per container per day and the daily rate usually rises the longer the container is held.
Definitions
The Digital Container Shipping Association (DCSA) defines the terms as follows:
- Demurrage: the charge the cargo party pays to the shipping line when a container remains inside the terminal or depot beyond the free time.
- Detention: the charge the cargo party or haulier pays to the shipping line for using the container outside the terminal or depot beyond the free time. In the United States this is often called per diem.
- Storage: the charge for the space the container occupies on the terminal beyond the free time, paid to the terminal, the port or the shipping line.
- Free time: the period in which a container can be used without additional charges.
The key difference: demurrage and detention pay for the carrier’s container, storage pays for the terminal’s ground. In Belgium, Maersk and Hapag-Lloyd fold storage into demurrage. Maersk’s Belgian import terms state that demurrage includes terminal storage costs. Hapag-Lloyd’s Belgian tariff lists storage as included and not charged separately. In other countries storage can be a separate invoice from the terminal.
When each clock runs
| Shipment | Demurrage | Detention | Combined demurrage and detention |
|---|---|---|---|
| Import | From discharge from the vessel until the full container leaves the terminal (gate-out) | From gate-out of the full container until the empty container is returned to the agreed depot or terminal (gate-in empty) | From discharge until the empty container is returned |
| Export | From gate-in of the full container at the terminal until it is loaded on the vessel | From pick-up of the empty container until the full container is delivered to the terminal | From pick-up of the empty container until loading on the vessel |
Source: Maersk terms for detention and demurrage. Other carriers use the same events, but the exact moment the clock starts can differ. Hapag-Lloyd’s Belgian import tariff, for example, starts demurrage on the day of discharge and starts detention at 00:01 on the first calendar day after pick-up.
Check how days are counted. Maersk counts free time in Belgium in calendar days and treats public holidays as normal calendar days, so a container discharged on a Friday uses up free time over the weekend.
Combined demurrage and detention
Some carriers do not split the two charges and give one combined free period from discharge until the empty container is back. Maersk’s terms describe demurrage and detention on one hand and combined demurrage and detention on the other as alternatives. The carrier states per country which one applies. A combined period gives you flexibility: if the container leaves the terminal quickly, you have more days to unload. A split model gives separate allowances for the terminal and for your premises. When you negotiate free time, ask which model applies.
Worked example from a published Belgian tariff
Hapag-Lloyd’s import tariff for Belgium, valid from 1 January 2026 until further notice, sets these daily rates for a 40’ standard container:
| Period | Import demurrage (sea terminal, storage included) | Import detention |
|---|---|---|
| Free time | 4 calendar days | 4 calendar days |
| Next period | 2 days at EUR 65 | 3 days at EUR 75 |
| Following period | 3 days at EUR 110 | 7 days at EUR 90 |
| Next period | 6 days at EUR 130 | Thereafter EUR 140 per day |
| Thereafter | EUR 185 per day |
Worked example F. For example, a 40’ container is discharged in Antwerp. Customs release comes late and the container leaves the terminal on the ninth calendar day, counting the day of discharge as day 1.
- Demurrage: days 1 to 4 are free. Days 5 and 6 cost 2 × EUR 65 = EUR 130. Days 7, 8 and 9 cost 3 × EUR 110 = EUR 330. Demurrage: EUR 460.
- Detention: the empty container goes back on the sixth detention day. Days 1 to 4 are free, days 5 and 6 cost 2 × EUR 75 = EUR 150.
- Total: EUR 610 for one container, before any other charges.
Tariffs change and contracts often have their own free time, so always check the tariff that applies to your booking. Maersk, for instance, applies the free time and charges that were valid on the price calculation date at origin.
What drives extra cost in Antwerp and Rotterdam
The most common reasons a container overstays its free time:
- No commercial release. The shipping line releases the container only once freight and charges are paid and the bill of lading is handled. In Antwerp the release runs through Certified Pick up, a mandatory digital platform: each release party must accept and pass on the release right, the transport company must link the driver and customs must give the green light. A missing step blocks pick-up.
- Late customs release. A declaration lodged only after arrival, a missing document or a physical inspection or scan can hold a container for days. Under the Union Customs Code an import declaration can be lodged before the goods arrive. See customs clearance and our guide to shipping documents.
- No transport capacity. Truck and barge slots are not always available on the day a container is released. In the week of 30 September to 6 October 2026, for example, barge delays were about 24 hours in Antwerp and 12 to 24 hours in Rotterdam.
- Busy terminals. High yard occupancy slows down deliveries and pick-ups. In the same week one Antwerp terminal reported high yard utilisation, especially for empty containers. One Rotterdam terminal reported 90% yard occupancy.
- Problems returning the empty container. Empty containers must go back to the depot named by the carrier. Returning to another depot is possible only with the carrier’s approval and against a drop-off fee.
- Unloading capacity at your site. If your warehouse cannot unload the container quickly, detention runs.
How to avoid demurrage and detention
- Ask for the free time in writing with every quote and check whether it is split or combined, in calendar or working days.
- If you know you need more time, negotiate extra free days at booking. Maersk, for example, lets importers buy extra detention days when booking.
- Prepare the customs declaration before the vessel arrives and make sure the commercial invoice, packing list and other documents are complete.
- Arrange the commercial release early: pay freight and charges and settle the bill of lading before arrival.
- Book the truck or barge for the release date and plan unloading staff and dock space.
- Follow the vessel’s estimated time of arrival. With schedule reliability around 50%, the real arrival day can move.
- Return the empty container promptly to the depot stated by the carrier.
- Check D&D invoices against the tariff, the free time agreed and the actual gate times.
With Destinex you have one personal contact for each shipment who keeps you updated proactively, so release, customs and haulage can be lined up before the free time starts.
Cargo to or from the United States
For US trades the Federal Maritime Commission’s rules on demurrage and detention billing (46 CFR Part 541) have applied since 28 May 2024. They set minimum invoice content and time limits for invoicing and disputes. In September 2025 a US court set aside one section, on which parties may be billed. The FMC then removed it. The other provisions remain in force. These rules do not apply to shipments between Europe and Asia.
Transit times: what makes up door-to-door
The sailing time in a carrier schedule is port to port. What you experience is door to door, which adds several steps before and after the voyage.
The building blocks
| Step | What happens | What can delay it |
|---|---|---|
| Pre-carriage | Pick-up at the supplier and transport to the port, airport or consolidation warehouse | Cargo not ready, truck availability, LCL consolidation waiting for the next sailing |
| Origin port | Export clearance, delivery before the cut-off, Verified Gross Mass (VGM) submitted, loading | Missed cut-off, missing documents, cargo rolled to a later vessel |
| Main voyage | Sailing including port calls on the route | Routing (Suez or Cape of Good Hope), weather, port congestion along the route |
| Transshipment | Container moved to another vessel at a hub port | Waiting for the connecting vessel |
| Destination port | Discharge, release, LCL unpacking at the warehouse | Terminal congestion, commercial release |
| Customs | Import declaration, possible inspection | Missing documents, inspection, HS code questions |
| On-carriage | Truck, barge or rail to your door | Haulage capacity, delivery appointments |
Since 1 July 2016 SOLAS requires a verified gross mass for every packed export container. It is a condition for loading the container onto a ship.
Why schedules vary and how reliable they are
Carrier schedules are plans. Port congestion, weather, changes in routing and blank sailings move them. According to Sea-Intelligence’s Global Liner Performance report, global schedule reliability was 49.9% in August 2026, the lowest level since September 2022. Vessels that arrived late were on average 6.81 days late. Reliability differs strongly between carriers and alliances, so build buffer into your planning, especially before production deadlines or promotions.
Red Sea, Suez and the Cape of Good Hope in 2026
From late 2023 most container services between Asia and Europe avoided the Red Sea and sailed around the Cape of Good Hope. In 2026 carriers started to return to the Suez route step by step. Maersk and Hapag-Lloyd (Gemini Cooperation) moved several Asia-Europe and Middle East services back to Suez during 2026, including four more services from September 2026. CMA CGM, MSC, OOCL and COSCO have also routed services through Suez again. The Premier Alliance of ONE, HMM and Yang Ming was expected to follow in October 2026. According to the Suez Canal Authority, 166 medium and ultra-large container vessels transited the canal in July to September 2026, compared with 16 in the same period of 2025.
The return is partial and conditional. Carriers state that they may move services back to the Cape if the security situation in the Red Sea deteriorates. Analysts such as Drewry point out that the risk has not disappeared. For you this means that two sailings on the same trade can have very different transit times. Ask which routing your specific sailing takes.
Indicative sailing times Asia to North Europe
As a rough guide to the effect of routing, the geography of the route is the starting point. For a vessel sailing from Shanghai to Rotterdam at 16 knots without port calls, the PortEconomics research network gives:
| Route | Distance | Pure sailing time at 16 knots |
|---|---|---|
| Via Suez Canal | about 10,600 nautical miles | about 27 days |
| Via Cape of Good Hope | about 13,800 nautical miles | about 35 days |
Real services call at several ports on the way. The same source puts a typical Asia-Europe service with 5 to 10 port calls at about 35 days via Suez. These figures are indicative only. They are not a schedule and not a Destinex transit time. Door-to-door time is longer, because it adds the steps in the table above. For a specific shipment, ask for the current schedule of the sailing you are booked on.
Who pays which costs: Incoterms
The Incoterms® 2020 rule in your sales contract decides which costs the seller pays and which the buyer pays. The full explanation is in our Incoterms guide. For freight costs the most important split is this:
| Incoterms® 2020 rule | Main carriage paid by | Unloading costs at destination | Import clearance, duties and import VAT |
|---|---|---|---|
| EXW | Buyer | Buyer | Buyer |
| FCA, FAS, FOB | Buyer | Buyer | Buyer |
| CPT, CIP, CFR, CIF | Seller | Buyer, unless they are part of the seller’s contract of carriage | Buyer |
| DAP | Seller | Buyer, unless they are part of the seller’s contract of carriage | Buyer |
| DPU | Seller | Seller | Buyer |
| DDP | Seller | Buyer, unless they are part of the seller’s contract of carriage | Seller |
In practice this means that an importer buying CFR or CIF often still receives an invoice for destination terminal handling and local charges at Antwerp or Rotterdam. Under EXW, FCA and FOB you also pay the main freight and its surcharges, including the emission and fuel surcharges described above. Incoterms do not name demurrage and detention. Who pays them depends on the contract with the carrier and on what you agree with your trading partner, so put it in writing.
How to get an accurate freight quote
The more precise the information, the fewer surprises on the final invoice. Send this with your request:
- Pick-up and delivery address with postcode (or the ports or airports if you only need port to port)
- Incoterms® rule and named place in your sales contract
- Description of the goods and HS code (see our guide to HS codes and EORI)
- Number of packages, packaging type, packed dimensions per package in cm and gross weight per package and in total
- Whether the goods can be stacked and how high
- For FCL: container type and number of containers
- Ready date and the latest acceptable delivery date
- Whether the goods are classified as dangerous goods or need temperature control, because this changes the options and the price
- Value of the goods and whether you want cargo insurance
- Who handles export and import customs clearance
- Delivery details: loading dock or tail-lift needed, opening hours, appointment required
- Expected frequency and volume per year, if this is a regular flow
When you receive quotes, ask these questions before comparing them:
- Is the price all-in or base rate plus surcharges? Which surcharges are “subject to” and not included?
- Until which date is the quote valid and which date determines the surcharges?
- Which destination charges are included?
- How many free days for demurrage and detention, split or combined?
- Which routing and transshipment ports does the sailing use?
- For road freight: which loading metre factor and which volume rule apply? Are tolls included?
You can contact Destinex with this information for a quote for sea freight, air freight or road freight.
Common mistakes that make freight more expensive
- Comparing an all-in price with a base rate. The cheaper-looking quote is often the one with surcharges still to come.
- Ignoring validity dates. Fuel and emission surcharges change monthly or quarterly. A quote from last quarter may no longer apply.
- Giving unpacked dimensions. Carriers measure the packed shipment including the pallet. Wrong dimensions lead to corrections on the invoice.
- Forgetting to mention that goods are stackable. In worked example D this alone made the difference between 4,200 kg and 2,700 kg chargeable weight.
- Assuming the same free time everywhere. Free time differs by carrier, port, container type and contract.
- Missing the destination charges. Under FOB or CFR purchases the destination terminal handling and local charges usually land on the importer.
- Booking the truck after the container is released. Every day of waiting can turn into demurrage.
- Returning the empty container to the wrong depot. This leads to drop-off fees or extra detention.
Glossary of freight cost terms
| Term | Meaning |
|---|---|
| BAF | Bunker adjustment factor, the fuel surcharge in sea freight. Carrier names include Fossil Fuel Fee (Maersk) and Marine Fuel Recovery (Hapag-Lloyd) |
| CAF | Currency adjustment factor, a surcharge for exchange rate movements |
| CBM | Cubic metre, length × width × height in metres |
| CFS | Container freight station, the warehouse where LCL cargo is consolidated or unpacked |
| Chargeable weight | The weight on which air or road freight is charged: the higher of actual and volumetric weight |
| Combined D&D | One free period and one charge for the time inside and outside the terminal |
| Demurrage | Charge for keeping the carrier’s container in the terminal beyond free time |
| Detention | Charge for keeping the carrier’s container outside the terminal beyond free time |
| EMS / ESS / ETS surcharge | Emission surcharges passing on EU ETS and FuelEU Maritime costs |
| Free time | Period in which no demurrage, detention or storage is charged |
| GRI | General rate increase announced by a carrier |
| ISPS | Security surcharge linked to the International Ship and Port Facility Security Code |
| LDM | Loading metre, one metre of trailer length across the full width of 2.40 m |
| OTHC / DTHC | Origin and destination terminal handling charges |
| PSS | Peak season surcharge |
| Revenue ton (RT) | Unit for LCL pricing: 1 CBM or 1,000 kg, whichever is greater |
| Storage | Terminal charge for the space a container occupies beyond free time |
| VGM | Verified Gross Mass, the verified weight of a packed container, required for loading |
| W/M | Weight or measurement, the LCL pricing rule |
Talk to us about your next shipment
Freight costs and transit times depend on details: the lane, the routing, the dimensions, the free time and the terms of sale. Destinex is based in Antwerp and works with the ports of Antwerp and Rotterdam. You get one personal contact for each shipment, reachable 24/7, who keeps you informed proactively. Ask for a quote and we will show you which charges apply to your shipment.
Last updated 22 October 2026